FAQs

Your payment obligations continue to apply in the ECC right up until four weeks after the supervisor has issued the defects certificate – see clause 50.1. That means that your project manager should be issuing certificates for payment throughout that period, even if they are zero valued. 

The contractor is paid the amount due – see clauses 50.2, 51.1 and 51.2. If the amount due reduces, presumably because of some wrongly assessed amount, the project manager can and should correct the amount due – see clause 50.5. If that reduces the amount due then the third sentence of clause 51.1 requires the contractor to make a payment for the difference to the employer. Therefore, in answer to your question, you are able to retrieve this overpayment from the contractor.  

In addition, the contractor is required to pay interest on the amount he has been overpaid, in exactly the same way as you are required to pay such interest on any underpayment – see  clause 51.3.  

What should happen is that your project manager makes an assessment based upon the agreed amount and issues a certificate requiring the contractor to pay the difference to you under clause 51.1. The contractor then pays you the certified amount in accordance with the timescales set out in clause 51.2. If the contractor is late in paying, then interest will accrue on that payment, again see clause 51.2.

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford