NEC Releases Y Clauses for use in Northern Ireland

NEC Releases Y Clauses for use in Northern Ireland

NEC has released suitable secondary Options for use in Northern Ireland to support projects under the Construction Contracts (Northern Ireland) Order.

The Housing Grants, Construction and Regeneration Act 1996 applies to construction contracts (defined in the Act) in England, Scotland and Wales. Option W2 was previously drafted for use in appropriate NEC contracts to provide for adjudication and Y(UK)2 for payment to incorporate the requirements of the Act. 

Northern Ireland introduced its own provisions under the Construction Contracts (Northern Ireland) Order 1997. The Northern Ireland Order has one difference which affects clause W2, relating to the effect of Sundays and public holidays on timescales. This Y(NI)1 clause is issued in response to industry requests to provide a stardard set of amendments to NEC contracts to replace the provisions with those in the Northern Ireland Order. The clause amends clause W2 (where applicable) to give effect to this change, and otherwise changes references to the Act to refer to the Northern Ireland Order. 

For construction contracts in Northern Ireland which are subject to the Order, in Contract Data part 1 “W2” should be included as the dispute resolution Option (where applicable), and “Y(UK)2” and “Y(NI)1” should be included as secondary Options. 

NEC wishes to thank William Brown of Fortfield & Brown who drafted these clauses.

Click here to download the Y(NI) Clauses 
Recent Projects

Recent news

Contract data part two: parts a client can complete pre-tender

Contract data part two: parts a client can complete pre-tender

‘ECC does not have a named contractor’s representative, so clients should ensure this is first job in the list to clarify who makes decisions on behalf of the contractor.’

Read more
How NEC is supporting growing use in international markets

How NEC is supporting growing use in international markets

Over the past few months NEC has continued to make strides with its range of products and services in the global arena.

Read more
Industry experts share practical insights on managing programmes under NEC4 Contracts

Industry experts share practical insights on managing programmes under NEC4 Contracts

Over 50 professionals from across the construction, project management and procurement sectors attended the NEC Hong Kong Workshop, held in June.

Read more
View all news