Landslip prevention and mitigation programme, Hong Kong

Landslip prevention and mitigation programme, Hong Kong
  • location:
    Hong Kong
  • Value:
    HK$16 million (£1.3 million)
  • Contracts Used:

    PSC, TSC

  • Start-Finish:
    2014 − 2019
  • Employer:
    Civil Engineering and Development Department (CEDD), the Government of the Hong Kong Special Adminis
  • Contractor:
    Aecom Asia Co. Ltd
  • Project Manager:
    Deputy Head (Landslip Preventive Measures), Geotechncial Engineering Office, CEDD

The Hong Kong government’s Civil Engineering and Development Department (CEDD) is trialling the NEC3 Professional Services Contract (PSC) on one of its many landslip prevention and mitigation programme consultancy contracts.

It is the first use of the PSC option C (target contract) for public works projects in Hong Kong. CEDD's geotechnical engineering office awarded the 5 year, HK$16 million (£1.3 million) contract to Aecom Asia Co. Ltd in April 2014.

CONSULTANCY SCOPE

CEDD‘s rolling landslip prevention and mitigation programme deals systematically with landslide risks throughout Hong Kong arising from both substandard man-made slopes and vulnerable natural hillside catchments.

Under the pilot PSC contract, Aecom is carryng out natural terrain hazard study for one hillside study area. The consultant will undertake detailed design, supervision and contract administration of landslip prevention and mitigation works for the hillside catchments and a total of 25 substandard man-made slopes and retaining walls.

The individual landslip prevention and mitigation works will be procured separately under an NEC3 Term Service Contract, tentatively scheduled for mid-2015.

PAIN/GAIN SHARE

"Under PSC option C the consultant is generally paid based on time charge," says senior geotechnical engineer Thomas Wong. "This option provides a mechanism for pain/gain share in respect of the consultancy fee, under which CEDD and Aecom share the difference between the actual price and the final target price."

For the pilot project Wong says a pain cap corresponding to 110% of the target price has been adopted by CEDD. ‘The pain/gain is shared equally between CEDD and Aecom unless the actual price is higher than the above pain cap, in which case the consultant bears all the pain beyond the pain cap.‘

Special provisions for interim assessment of the consultant‘s pain share have also been incorporated in the contract to avoid over-payment and undue front-loading.

"The pain/gain share mechanism should, in principle, drive the contracting parties to a common goal of completing the services more efficiently in terms of cost and time – this will be carefully reviewed at the end of the pilot scheme," says Wong.
‘So far, the contract is proceeding smoothly and the consultant is able to achieve all the key dates stipulated in the scope. CEDD is partnering with Aecom as a team and the working relationship has been good.‘

BENEFITS OF NEC3

  • NEC3 Professional Services Contract option C provides a mechanism for pain/gain share in the consultancy fee.
  • Pain/gain share mechanism drives contracting parties to common goal of completing services more efficiently in terms of cost and time.
  • Contract encourages employer to partner with the consultant, leading to a good working relationship.

Further Information

Contact: Thomas Wong, Senior Geotechnical Engineer/Project Management 1, Geotechnical Engineering Office, CEDD
Tel: +852 2760 5773
Email: thomaskcwong@cedd.gov.hk
Web: www.cedd.gov.hk/eng/projects/landslip/index.html

Back to Previous PageBack

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford