The first point is to question why you made such an agreement with your project manager. If it causes such problems, then insist the project manager deals with your quotations within the time scales set out in clause 62.3. If the project manager fails to do so then notify him or her of that failure under clause 62.6.

If the project manager continues to fail to reply for 2 weeks after that notification, then your original quotation will be treated as accepted (clause 62.6) and therefore implemented (clause 65.1), after which only the adjudicator can change it. The timescales in the ECC (and the NEC3 Engineering and Construction Subcontract) are deliberately written so that you should not need to get yourself in this position.

The answer to the second question is that this excess amount is not a disallowed cost, simply because it is not stated within the list of disallowed cost items stated in clause 11.2(25).



Related Products

Copyright © NEC® Contracts 2018, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford