Regarding your first query, there seems to be no provision that allows the project manager to refuse to certify such amounts. The costs are part of the defined cost because they fall within the bullet of clause 11.2(23) and they do not fall within any of the stated reasons for disallowed cost set out in clause 11.2(25).

On the latter, note that the bullet on procurement procedure refers only to such procedures set out in the works information. The project manager's practical remedy is to instruct the contractor to stop work under clause 34.1 on the work the subcontractor is carrying out. Although this would be a compensation event, it would carry no time or cost implications because it arises from the contractors fault - see the second sentence of clause 61.1

Regarding your second query, an hourly paid labour-only subcontractor does not fall within the definition of a subcontractor in clause 11.2 (17), in that they do not fall within any of the bulleted points. Instead, they only have a contract to send persons to site to work under the contractor's instructions. The contractor is paid for such in accordance with item 14 of the schedule of cost components, to which is added the working areas overhead percentage. If though the labour-only subcontractor had a contract to carry out a specific item of work and is paid based upon the amount of work it does, then it will be a subcontractor under either of the first two bullets.



NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford