Clause 20.1 states that the consultant provides the service in accordance with the scope. Clause 11.2(12) says to provide the service means do the work necessary to complete the service and all incidental work which the contract requires. The scope is information which specifies and describes the service. Accordingly, someone who is providing part of the service must be carrying out actions to provide the service. Therefore, the distinction between people who are covered by item 1 of the schedule of cost components and support people is established by what the scope states the consultant must do.


In your case, the person has been administering document control and weekly time sheets. If the scope specifies that a document control system must be provided, and that weekly time sheets are to be submitted to the service manager, then this person is clearly providing part of the service. Additionally, if you can demonstrate that such work is necessary to comply with some contract requirement – such as quality control requirements set out in the contract or evidence of defined cost – then again, that person would be providing part of the service.

If, however, the contract has no requirement for such work, and you are simply applying your own management processes to ensure your own documents are kept in order and timesheet records are able to support payment to people, then the person would not be providing a part of the service. In that case they would be included as part of your support people, because there is no requirement in the contract that this work has to be done.



This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy