FAQs

The contractor’s obligation is to achieve completion by the completion date, see clause 30.1. It cannot stop work while waiting for a compensation event quotation is agreed, see the last sentence of clause 61.1. If the contractor does stop work, the compensation event will be assessed as if they did not do so, see clause 63.7, which will put them in danger of breaching clause 30.1 and having delay damages levied.

The issue as to termination is dealt with in clauses 90 and 91. The employer can terminate if you have notified that the contractor has defaulted by substantially failing to comply with its obligations and not put that default right  within 4 weeks of the notification, see clause 91.2 (R11). In summary the contract already deals with these issues and nothing further is needed.

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy