Frequently Asked Questions

Question

Under the NEC3 ECS June 2005.

2 Subcontractor' main responsibilities;

Working with others 25;

Clause 25.3 refers to the Contractor's right to recover additional costs should the Subcontractor fail to meet a Key date set within the Subcontract. The last sentance within this clause states 'The Contractors right to recover the additional cost is his only right in these circumstances'. Is this effectively a time bar clause whereby if the Contractor does not assess within the period stated then he loses his right to recover the additional costs?

If the Contractor assesses the additional cost are the costs open to verification?

No, this is not meant to be a time bar, and it does not act as one.  Not meeting a Key Date is a breach of clause 30.3 of the contract.  In that case the Contractor could try to recover damages in law for that breach rather than the more limited amounts set out in clause 25.3, i.e. “on the same project”.  The last sentence of 25.3 ensures that the Contractor cannot do so, and that their only right is to use the calculation based upon cost incurred only “on the project”.

As a final point it is important to understand that clauses 30.3 and 25.3 only apply to those Key Dates that are listed in the Subcontract Data Part 1 of your contract.  Key Dates cannot be added by the Contractor at will, they have to be in the contract.

Back to FAQs