From the question we are not sure what design you are referring to, but let us assume this is works information for the contractor’s design as set out in contract data part two. In that case, the design is part of the works information (see the words used in the contract data) and is binding on both parties. Your project manager is however entitled to change any of the works information, whether it is that provided by you or the contractor – see clause 14.3. That instruction will normally be a compensation event under clause 60.1(1) but that clause does have some exceptions to that general rule, as set out in the clause itself. One of those exceptions is an instruction to change the works information provided by the contractor for its design to comply with works information provided by the employer (see 2nd bullet of clause 60.1(1)). Your project manager can therefore instruct a change to the works information provided by the contractor for it to comply with the works information provided by you, and that will not be a compensation event. However, such changes can only be made to make it comply with the original works information provided by you – any other ‘nice to have’ changes will result in a compensation event occurring.

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy