FAQs

Without an accepted programme the contract cannot be administered as properly intended. See for example the compensation events that rely upon an accepted programme - clauses 60.1(2) (3) and (5) - also operating clause 63.3 is obviously a problem. 

The lack of a programme is probably indicative of one of two things. Either the contractor is disorganised and has no control of progress, or the contractor has a programme that it does not want to show you. Neither is good news for your project and both must be avoided.

Without an accepted programme the assessment of all compensation events is taken out of the hands of the contractor altogether. The project manager is required to reject all compensation event quotations and make his or her own assessment of each compensation event - see the 3rd and 4th bullet points of clause 64.1. That assessment must be made using the project managers assessment of the programme of the remaining works - see clause 64.2

As for when the 25% is released, the contract is silent because it did not envisage that any contractor would allow such a situation to occur given that cash flow is the life blood of any contractors business! The project manager should notify an early warning to the contractor and make sure that senior members of the contractors management attend a risk reduction meeting to sort the problem out.



NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford