FAQs

The simple answer is that the contractor in an ECS can issue an instruction to change the subcontract works information (see clause 14.3) and there is no contractual limit to the contractor doing this. However, the instruction not to carry out the work will be a compensation event, which will be valued based upon the forecast reduction in defined cost to carry out the work it has caused plus the fee. It is not just a case of deleting the priced items in the activity schedule. 

If you can show that the cost of the deleted work, in terms of defined cost plus your fee, is lower than the price in the activity schedule, then the contractor will have to pay you the difference. You could also argue that if the contractor can get the deleted work done cheaper then so could you by sub-sub-contracting it to the same people, such that the contractor will save very little. That would be especially so if you can show that you could not instantly pick up work to cover the resources you would have used, in which case you could include the forecast cost of those resources as well. But, in doing so, you do need to remember that you must act promptly and competently to any instruction (see clause 63.7).

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy