It is a moot point as to whether you can or cannot provide revised quotations. Whatever the answer, project managers cannot just ignore or reject them out of hand. Project managers are obliged to decide if your quotation has been correctly assessed or not. That obligation is not just about whether it is too high; they must also object if they think it is too low. Therefore if they think your revised assessment is correct (or a part of it), then they should either instruct you to provide a revised quotation with reasons (clause 62.3), or makes their own assessment (clause 64.1). If project managers choose the latter, then they must include whatever they think is correct, which can and should include part or all of your revisions, if they think these are correct.

Of course if project managers think that both your original assessment and your revised assessment are wrong, then they are entitled to reject them both and make their own assessment. Once notified, only the adjudicator can change it (clause 65 and W2.3).



Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy