Under option E you will be paid for the defined cost of the works plus your fee – see clauses 50.2 and 11.2(29). Defined cost is a defined term (see clause 11.2(23)) and is calculated using the schedule of cost components. The schedule of cost components therefore sets out what you will get paid and how it will be calculated. Clause 52.1 makes it clear that any cost not included in the schedule of cost components will need to be allowed for in the fee, that is the fee percentages you quote in the contract data part two of the ECS (see clause 11.2(8)).

Section 1 of the schedule of cost components deals with the cost of people. We assume that the people that you recruited worked for you directly and therefore the costs you will recover are set out in items 11, 12 and 13 of the schedule of cost components. Recruitment costs for people are not listed here and therefore they are not paid, and are assumed to be in your fee. It is not that they are a disallowed cost, they are just not ‘allowed’ in the first place because they do not form part of the definition of defined cost.
Under option E you will be paid for the defined cost of the works plus your fee – see clauses 50.2 and 11.2(29). Defined cost is a defined term (see clause 11.2(23)) and is calculated using the schedule of cost components. The schedule of cost components therefore sets out what you will get paid and how it will be calculated. Clause 52.1 makes it clear that any cost not included in the schedule of cost components will need to be allowed for in the fee, that is the fee percentages you quote in the contract data part two of the ECS (see clause 11.2(8)).

Section 1 of the schedule of cost components deals with the cost of people. We assume that the people that you recruited worked for you directly and therefore the costs you will recover are set out in items 11, 12 and 13 of the schedule of cost components. Recruitment costs for people are not listed here and therefore they are not paid, and are assumed to be in your fee. It is not that they are a disallowed cost, they are just not ‘allowed’ in the first place because they do not form part of the definition of defined cost.

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy