The logic of clause 63.2 is that there may be compensation events that occur that reduce the defined cost where the risk and reward should lie with the contractor. The obvious example is clause 60.1(12), where the physical conditions may be better than expected. The exceptions stated in the contract are to be found in the other sub-clauses of clause 63 set out in the main option specific clauses (as well as some of the secondary options), so see clause 63.10 in Options A and B and 63.11 in Options C and D.
You will see that generally the secondary option clauses allow for the reduction if the event is an instruction to change the works information. The only exception to that is in Options C and D, when the instruction to change the works information resulted from a proposal by the contractor which the project manager accepted – see the first bullet of clause 63.11 and compare it with the same bullet in clause 63.10.

With a risk-sharing contract, such as Options C or D, the contractor should be able to share in the benefits of the cost savings that it has proposed through the share mechanism set out in clause 53. You should remember that in these options the value of the compensation event only changes the ‘target’ and not what the contractor actually gets paid for carrying out the work, and therefore the contractor will never ‘pocket the difference’, as you suggest. Instead it would be the employer that did the ‘pocketing’.
 

Related Products

This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy