NEC3: How to provide for early contractor involvement using an ECC Contract
The purpose of this guide is to help users implement an early contractor involvement (ECI) approach using the NEC3 Engineering and Construction Contract (ECC).
ECI, where a contractor takes part in the design development and construction planning stage of a project, is now widely recognised as beneficial. This document also provides a model clause and guidance to allow for ECI using the ECC.
Foreword
Preface
Acknowledgements
Part 1 Introduction
Part 2 Special issues relevant to ECI contracts
- Budget for scheme
- Selection of team members
- Design options
- Use of secondary Option X12 partnering
- Additional designer requirements
- Definition of stages
- Split payment between stages
- Control of costs in Stage One
- Submission of design proposals
- Establishing price/target/forecast for Stage Two
- Incentivisation in Stage Two
Part 3 Guidance on model clause
- Guidance on this additional clause
- Definitions
- Forecasts
- Proposals for Stage Two
- Notice to proceed to Stage Two
- Changes to the Budget
- The Parties’ use of material
- Incentive payment
Appendix 1 Model clause
Additional clause for use with the NEC3 Engineering and Construction Contract
(ECC) Options C and E
Additional ECC Contract Data entries
Appendix 2 Additional material required in Works Information
Users should note that the NEC Forms of Contract are protected by copyright and may not be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical or photocopying, recording or otherwise, without the prior permission of the copyright owner. However, Contract Data forms may be reproduced for the purpose of obtaining tenders, awarding and administering contracts.
Likewise, plagiarising any copyrighted document is illegal. For users seeking to prepare their own bespoke contracts based on the NEC Forms of Contract, please contact NEC at info@neccontract.com to discuss and obtain a copyright licence.
ePrint (ePrint)
Product code: L08043-P
ISBN:
9780727761750
eView (eView)
Product code: L08043-V
ISBN:
9780727761750