Introducing Secondary Option X29 Climate Change

Introducing Secondary Option X29 Climate Change

The world is facing a climate change emergency and the creation and operation of built assets is a contributor to the problem. The sustainability of creating and operating buildings and infrastructure will need to dramatically increase in order to achieve net zero emissions of carbon dioxide and other climate-warming gases.

Reducing the impact of creation, operation, maintenance and disposal of assets on climate change is principally a technical issue addressed in the Scope. However, there are limitations in this approach as it relies on users including the required content in the Scope and linking this to the contractual processes in the contract.

Introducing additional conditions of contract was seen as beneficial in driving the reduction of the impact of the works on climate change.

  • Signposting to the issues to be covered in the Scope / raising its profile
  • Incentivising performance against climate change targets
  • Adding to existing processes or creating new processes that support the reduction of the impact of the works, service and supply on climate change

This has led to the development of X29.

Combatting climate change has to be considered at every point in the life of an asset and needs the engagement of clients and all key members of the supply chain. To support this a version of secondary Option X29 has been produced for all NEC4 main and main subcontract forms.

We welcome feedback on the use of secondary Option X29 and are keen to support the capture and development of best practice examples and look forward to engaging with users to do this.


Download the X29 clauses

Download the X29 Guidance Notes


The Institution of Civil Engineers (ICE) acknowledges the help in preparing secondary Option X29 given by the NEC4 Contract Board, the ICE Carbon Project and
  • Richard Patterson, BA MBA CEng FICE, NEC and Procurement Specialist and Technical Principal, Mott MacDonald. 
  • Siu Fa Ng, MSc CEng MICE, Project Executive, Environment Agency 
  • Stacey Collins, Major Projects Partner & Climate Change Specialist, at global law firm Pinsent Masons LLP 
  • Veronica Flint Williams, BEng CEng FICE, Contract and Risk Manager, Environment Agency 

The NEC4 Contract Board is: 
  • P Higgins, BSc (Hons), CEng, FICE (Chair) 
  • P T Cousins, BEng (Tech), DipArb, CEng, MICE, FCIArb 
  • M Garratt, BSc (Hons), MRICS, FCIArb 
  • I Heaphy, BSc (Hons), FRICS, FCIArb, FCInstCES, MACostE 
  • S Jackson, LLB, LLM, MSc, FCIArb, FCInstCES 
  • S Rowsell, BSc, CEng, FCIHT, MCIPS 
Recent Projects

Recent news

Understanding the contractual and legal roles of NEC project managers

Understanding the contractual and legal roles of NEC project managers

This article looks at the role of the NEC4 ECC project manager, when they are required to make decisions involving acceptance of programmes and assessment of compensation events.

Read more
NEC updates Y(Aus) clauses for security-of-payment compliance

NEC updates Y(Aus) clauses for security-of-payment compliance

NEC has released an updated set of Y(Aus) clauses for Australia. The latest revision specifically updates the clauses for Western Australia.

Read more
NEC4 option Z for additional contract conditions: clarity or curse?

NEC4 option Z for additional contract conditions: clarity or curse?

NEC contracts are frequently accompanied by pages of option Z additional conditions of contract. However, that they should be kept to a minimum and used where necessary.

Read more
View all news