We have an ECC option C (target cost with activity schedule) contract. Would the employer have an obligation to pay contractor pension shortfall (incurred by other means?)
The simple answer is yes, but only the amount that relates to the time people spent in your particular working areas. If the person was on your site for a year, but in the pension scheme for 10 years, then the employer would pay only for your 1 year of catching up.