Frequently Asked Questions

Question

If we have a compensation event and we also have a rate for this in the Price List do we use the Price List rate or assess this on Defined Cost?

Clause 63.1 defines that if you have a compensation event which only effects the quantities in the Price List then you would assess this by multiplying the changed quantities by the appropriate rates in the Price List

Back to FAQs