Hunua 4 Water Main, New Zealand

Hunua 4 Water Main, New Zealand
  • location:
    Auckland, New Zealand
  • Value:
    NZ$120 million (£59 million)
  • Contracts Used:

    ECC, SC

  • Start-Finish:
    2012 − 2016
  • Employer:
    Watercare Services Limited
  • Contractor:
    Fulton Hogan John Holland joint venture
  • Project Manager:
    Watercare Services Limited

Watercare provides water and wastewater services to around 1.5 million people in the Auckland region of the North Island, New Zealand. The company commissioned the Hunua 4 water main project as part of its long-term supply strategy to cater for the region’s future growth, including improving water supplies to the southern suburb of Manukau and providing system redundancy to the central business district.

The project involves constructing a new 28km pipeline between Watercare’s existing reservoirs at Redoubt Road in Manukau Heights and the Khyber Pass reservoir complex in the city centre. Stage 1 involves building the water main from Manukau to the suburb of Epsom. It consists of over 22km of pipeline ranging in diameter from 1.6m to 1.9m.

ECC OPTION A AND SC

Watercare awarded the NZ$120 million (£59 million) NEC3 Engineering and Construction Contract (ECC) option A (priced contract with activity schedule) for stage 1 to a joint venture of contractors Fulton Hogan and John Holland.

Stage 1 is being constructed predominantly by open-cut methods through variable ground conditions ranging from soft peats through to hard basalts. There is also a tunnelled section under motorway SH1 and pipe bridges over motorway SH20 and several streams.

Work started in May 2012 and is due for completion in June 2016.  By the end of 2014, over 14km of 1.9m diameter pipeline had been installed, with 7.5km of this already commissioned and in service.

The key equipment for the contract was procured using the NEC3 Supply Contract (SC). This consisted of valves and concrete-lined steel pipe, which had a total cost of NZ$55 million (£27 million).

CO-LOCATED PROJECT TEAM

To help foster a ‘spirit of mutual trust and cooperation’ between the parties as required by NEC, Watercare, the joint venture contractors and the consultants CH2M Beca and GHD are co-located in a single project office.

According to Watercare’s project manager David Moore, ‘The success of the NEC has been the way it encourages a proactive approach between the parties to overcome problems faced during construction − such as stakeholder issues, contaminated land, unknown utilities and traffic.

Through weekly meetings and collaborative working practices, all issues have been effectively monitored and managed through the NEC compensation-event process.  The approach has resulted in a very strong and positive working relationship developing between all of the parties.’

To assist in administering the project, Watercare is using a web-based contract change management application from NEC licenced content partner Conject.

BENEFITS OF NEC

  • Project team members are required to work in a spirit of mutual trust and cooperation.
  • Encourages a proactive approach between all parties to overcome problems faced during construction.
  • All issues are effectively monitored and managed through compensation events.
  • Results in a very strong and positive working relationship within the project team.

Further Information

Contact: David Moore, Watercare
Tel: +64 9 539 7871
Email: dmoore@water.co.nz
Web: www.watercare.co.nz

Back to Previous PageBack

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford