Comparison of the PSSC with the PSC

Comparison of the PSSC with the PSC

The NEC4 Professional Service Contract (PSC) and the NEC4 Professional Service Short Contract (PSSC) have been around for many years. The PSSC is a simplified and shortened version of the PSC, including procedures which are simpler to manage and appropriate for priced contracts of low risk and low complexity.

However, often Clients and Consultants often get used to the PSC and do not consider the shorter version even if it might be more appropriate for the contract in question.

The short contract does not manage the risks in the way the PSC does (e.g. in the PSSC the Consultant includes a quotation with its notification of a compensation event; if a quotation is not accepted the Client makes its own assessment). However, for many relatively straight forward contracts, the PSSC will be the better option.

The new guidance note provides a comprehensive breakdown of the differences between the PSC and PSSC. Developed by Richard Patterson, NEC and Procurement Specialist, Mott MacDonald, with assistance from the NEC Contract Board, the document expands upon existing Mott MacDonald literature and NEC is pleased to be making it more widely available.

 View the Guidance Note
Recent Projects

Recent news

Richard Patterson – 100 not out for NEC

Richard Patterson – 100 not out for NEC

With this issue of the NEC Insights Briefing, Richard Patterson has now racked up an astonishing 100 contributions. We therefore thought it was time to learn more about the man behind it all.

Read more
NEC in the UK dredging sector: how to use Option selection and Contract Data to make it work

NEC in the UK dredging sector: how to use Option selection and Contract Data to make it work

NEC has become a mainstream form for UK dredging/coastal works, but it is not ‘one-Option-fits-all’. David Kinlan & Richard Patterson review how Option selection and Contract Data should be used.

Read more
Building better together: evolving construction contracts from adversarial to collaborative

Building better together: evolving construction contracts from adversarial to collaborative

Over the last three decades, collaboration has moved from being a desirable aspiration in construction projects to an explicit objective.

Read more
View all news