The 10.3 m diameter and 170 m long machine, called Florence, was procured by contractor Align – a joint venture of Bouygues Travaux Publics, Sir Robert McAlpine and Volker Fitzpatrick − from German manufacturer Herrenknecht using an NEC3 Supply Contract (SC). Together with its 2000 t sister machine Cecilia, it will complete the 16 km long twin 9.1 m diameter Chiltern tunnel in around 3 years.
Align is engaged under a £1.6 billion NEC3 Engineering and Construction Contract (ECC) Option C (target contract with activity schedule) for the Chiltern tunnel and Colne Valley viaduct (see Issue 108).
Contractor SCS Railways – a joint venture of Skanska, Costain and Strabag − is also using NEC3 SC to procure seven TBMs to work on the Euston and Northolt tunnels, for which it has two ECC Option C contracts worth £3.3 billion. In addition, the BBV joint venture of Balfour Beatty and Vinci is using NEC3 SC to procure the remaining TBM for the Long Itchington Wood tunnel in Warwickshire from Herrenknecht (pictured on page 1).
The TBMs are understood to be worth an average of around £15 million each.
First of 10 NEC-procured tunnel boring machines starts work on HS2 in the UK
Recent news
Collaboration – we need to ensure it is not just another buzzword
NEC Contracts' requirement to act in a 'spirit of mutual trust and co-operation’ are important words that require you to do more of the right thing than perhaps most of us are comfortable doing.
NEC set for greater use in Peru after seven years’ success
Mark Griffin, Project Director at Gleeds del Peru discusses the use of NEC in Peru to date and what the future may hold.
Introducing new Carbon in Infrastructure Procurement training: a practical approach to decarbonisation
ICE Training's new Carbon in Infrastructure Procurement course offers a unique and practical approach to managing carbon emissions through procurement processes.