Issuing payment notices on time

Issuing payment notices on time


Amendments to the UK Construction Act following the Local Democracy, Economic Development and Construction Act 2009 have resulted in a series of cases coming before the courts in the last few years looking at the effect of a failure to issue correct payment notices and whether the actual value of the works can then be disputed.

The November 2016 case of Universal Piling & Construction v. VG Clements [2016] EWHC 3321 (TCC) considered these issues in the context of the NEC3 Engineering and Construction Short Subcontract (ECSS).

Two adjudications

Following completion of the subcontract works, the subcontractor issued an assessment and application for payment to the main contractor. Due to the lack of any payment or pay-less notices from the main contractor, the subcontractor initiated an adjudication and was awarded the full amount.

However, 11 months later, the main contractor issued a defects certificate followed by a payment and pay-less notice to the subcontractor, which stated the completed works were worth less than the subcontractor’s previous assessment.

The contractor then started an adjudication to determine the final valuation of the works. The subcontractor argued this was already determined in the first adjudication, and could only be re-opened by a tribunal.

Court decision

A Technology and Construction Court judge began by looking at the wording of ECSS clause 50.1. She said the clause imposed an obligation on the subcontractor to assess amounts due and issue applications for payment by each assessment day until the month after the defects certificate has been issued.

However, she said the subcontractor’s assessments and applications were not conclusive as the price for work done to date had to be ascertained on an objective basis. She went on to hold that the issue in the second adjudication was not the same as the first, since it concerned the value of the works at a different date and included the release of retention. On that basis, the second adjudicator had jurisdiction to determine the final value of the subcontract works.

The judge then considered the maincontractor’s argument that it was entitled to issue a payment notice since the subcontractor failed to issue a further assessment and application following the defects certificate. She said this was an issue to be determined in the second adjudication, as well as whether the main contactor’s remedy was in fact a claim for breach of contract or that some other type of relief should be sought.

Conclusion

This decision is typical of the issues that have come up due to the increase in adjudications based purely on lack of payment notices, referred to by some as ‘smash and grab’ adjudications. Following NEC contract procedures and ensuring valid notices are issued on time will help to avoid such issues.
 
Recent Projects

Recent news

Spotlight Podcast Episode 1: NEC for Rail: A conversation with Mark Thurston and Keith Lomas, HS2

Listen to NEC Spotlight Podcast Episode 1: NEC for Rail: a Conversation with Mark Thurston and Keith Lomas, HS2

In July 2022, Mark Thurston, Chief Executive Officer, and Keith Lomas, Project Client Director, from HS2 recorded the first episode of the podcast to talk about NEC for the rail industry.

Read more
HS2 awards final NEC station contract on first phase from London to Birmingham

HS2 awards final NEC station contract on first phase from London to Birmingham

HS2, currently the world’s largest NEC-procured project to date, has let the last of four new high-speed railway stations on the £45 billion first section between London and Birmingham.

Read more
How NEC contracts can help us to achieve net zero carbon emissions

How NEC contracts can help us to achieve net zero carbon emissions

Recent record-breaking temperatures in the UK and across the world have reminded us, yet again, of the impact of climate change on our ability to function as a society and economy.

Read more
View all news