NEC issues NEC4 Practice Note

NEC issues NEC4 Practice Note


NEC has issued a free Practice Note for assessing delays due to compensation events.

The Practice Note has been prepared for use on the NEC4 Engineering and Construction Contract and the approach should be followed on other NEC4 Contracts.

Assessing delays to Completion Dates and Key Dates due to a compensation event can be a complex area where differing practices are emerging, and this Practice Note has been drafted to assist users in this particular area in practical usage of the contracts.

This Practice Note has been prepared by Peter Higgins, Matthew Garratt, Ian Heaphy and David Morrice.

This has been updated, the version is available via button below.

Download it here
 
Recent Projects

Recent news

NEC Contracts and Project 13 publish new guidance on NEC for Enterprise models

NEC Contracts and Project 13 publish new guidance on NEC for Enterprise models

NEC Contracts and Project 13 have jointly published new guidance on the use of the NEC4 suite within Enterprise models.

Read more
The Case for Alliancing

The Case for Alliancing

Alliancing is gaining popularity as clients look for different ways to deliver complex projects.

Read more
Delivering continuity in infrastructure programmes: the role of NEC

Delivering continuity in infrastructure programmes: the role of NEC

Six years of delivering infrastructure programmes in Peru have shown that maintaining continuity amid constant change is a major challenge. Structured NEC contractual frameworks help address it.

Read more
View all news