NEC issues NEC4 Practice Note

NEC issues NEC4 Practice Note


NEC has issued a free Practice Note for assessing delays due to compensation events.

The Practice Note has been prepared for use on the NEC4 Engineering and Construction Contract and the approach should be followed on other NEC4 Contracts.

Assessing delays to Completion Dates and Key Dates due to a compensation event can be a complex area where differing practices are emerging, and this Practice Note has been drafted to assist users in this particular area in practical usage of the contracts.

This Practice Note has been prepared by Peter Higgins, Matthew Garratt, Ian Heaphy and David Morrice.

This has been updated, the version is available via button below.

Download it here
 
Recent Projects

Recent news

How clients can set the rules for looking after subcontractors

How clients can set the rules for looking after subcontractors

This article sets out some simple actionable ways clients can take the lead and champion a fairer construction industry.

Read more
New three-level learning pathway launched for NEC users in Peru

New three-level learning pathway launched for NEC users in Peru

NEC has collaboratively developed a three-level learning programme for our NEC users in Peru.

Read more
JTC awards Singapore’s first public sector New Engineering Contract 4 collaborative contract for Jurong Innovation District

JTC awards Singapore’s first public sector New Engineering Contract 4 collaborative contract for Jurong Innovation District

JTC has awarded a collaborative contract for infrastructure works at CleanTech Park in Jurong Innovation District (JID) to Eng Lam Contractors Co (Pte) Ltd.

Read more
View all news