NEC issues NEC4 Practice Note

NEC issues NEC4 Practice Note


NEC has issued a free Practice Note for assessing delays due to compensation events.

The Practice Note has been prepared for use on the NEC4 Engineering and Construction Contract and the approach should be followed on other NEC4 Contracts.

Assessing delays to Completion Dates and Key Dates due to a compensation event can be a complex area where differing practices are emerging, and this Practice Note has been drafted to assist users in this particular area in practical usage of the contracts.

This Practice Note has been prepared by Peter Higgins, Matthew Garratt, Ian Heaphy and David Morrice.

This has been updated, the version is available via button below.

Download it here
 
Recent Projects

Recent news

NEC4 option Z for additional contract conditions: clarity or curse?

NEC4 option Z for additional contract conditions: clarity or curse?

NEC contracts are frequently accompanied by pages of option Z additional conditions of contract. However, that they should be kept to a minimum and used where necessary.

Read more
Avoid a battle of the forms by using a single set of terms and conditions

Avoid a battle of the forms by using a single set of terms and conditions

To avoid unnecessary disputes, NEC4 FC work orders should ideally be let under other NEC4 contracts and include the same contract data.

Read more
NEC used to deliver world-leading cancer research centre in Manchester, UK

NEC used to deliver world-leading cancer research centre in Manchester, UK

The Paterson Building in Manchester, UK is one of the world’s leading cancer research centres.

Read more
View all news