New NEC4 Practice Note - Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

New NEC4 Practice Note - Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

This practice note has been prepared due to feedback from UK based users who would like to use an independent Dispute Avoidance Board (DAB), rather than using the parties’ Senior Representatives to resolve disputes in a contract where W2 would normally be used. The DAB would be similar to that contained in Option W3 of the NEC4 Engineering and Construction Contract (ECC), as part of a consensual dispute resolution process.

Download Practice Note.
 

Practice Note 1 - Assessing delays due to compensation events - has also been updated.

Download Practice Note.

Recent Projects

Recent news

Environment Agency uses NEC4 to procure ultra-sustainable flood protection scheme

Environment Agency uses NEC4 to procure ultra-sustainable flood protection scheme

The Environment Agency in England, an NEC Users’ Group silver member, has used NEC to deliver one of its most sustainable coastal flood protection schemes to date.

Read more
NEC publishes new practice note on X22 early contractor involvement

NEC publishes new practice note on X22 early contractor involvement

NEC has published a new practice note on using option X22 on early contractor involvement (ECI) in the NEC4 Engineering and Construction Contract (ECC) Option C and Option E.

Read more
Airport Authority Hong Kong completes third NEC contract

Airport Authority Hong Kong completes third NEC contract

Authority Hong Kong (AAHK) has used NEC4 to procure a major newly completed office building in the middle of Hong Kong International Airport.

Read more
View all news