Top Prizes for New School

Top Prizes for New School

The NEC-procured Marlborough Primary School in Chelsea, southwest London won numerous awards last year. These included the Social Infrastructure Project of the Year Award in the 2018 British Construction Industry Awards (BCIA) as well as the Royal Institute of British Architects’ (RIBA) 2018 London Award and National Award. The BCIA judges described it as, ‘A magnificent success, using creating thinking’, while RIBA praised it as, ‘a terraced place of learning that is readable, fresh and distinctive.’

The new 458-place school for children aged from 3 to 11 replaced an outmoded Victorian school on a constrained urban site. It was part of a regeneration masterplan designed by architect Dixon Jones, which included an adjacent warehouse site owned by retailer John Lewis. The new school, plus an interim school in the warehouses to cover the two-year construction period, was funded by John Lewis under section 106 of the Town and Country Planning Act 1990.

The Royal Borough of Kensington and Chelsea engaged contractor Mace through the SCF public-sector construction framework to develop the approved scheme design, from RIBA stage 3 through to construction under an NEC3 Engineering and Construction Contract Option A (priced contract with activity schedule). Lendlease was appointed project manager and Mace engaged the original design team, including Dixon Jones, structural engineer Waterman and services engineer Arup.

On time and budget

Work started on the interim school in November 2014, demolition of the old school started in September 2015 and the new school was completed on time and budget in August 2017.

The new five-storey reinforced concrete, brickand stone-clad school building provides a total of 4,905m2 naturally ventilated internal space and features a series cascading, landscaped roof-top play decks. Totaling over 2,500m2, these outdoor spaces are made from soft play surfaces laid on a sub-base over open-joint concrete block ballast and 180 mm thick rigid insulation.

The Royal Borough also commissioned Mace to design and build a new commercial building at the north-west end of the site at the same time as the school, but under a separate £9 million NEC3 ECC Option A contract. Known as 50 Sloane Avenue, the steel-framed, brick-clad construction provides 2,100m2 of office space on four floors plus three retail units on the ground and basement levels. It also creates a new pedestrian link across the site along its retail frontage.

Collaborative approach

The Royal Borough’s capital programme manager Guy Parks commented, ‘We chose to use NEC to procure our new school and commercial building as it is the UK government’s preferred form of contract. It also espouses working in a “spirit of mutual trust and co-operation,” which we fully support.’

He says the NEC early warning system worked well. ‘The contractor provided all the cost and time implications of any changes so that there were no surprises at the end of the contract. Overall we believe NEC helped us to develop an open and collaborative approach on the project, with all of us working as a team. This is evidenced by a superb result in the final building, which is well-liked by the school and local community.’

Nick Abbey, framework director at Mace, says, ‘It was only down to the collaborative approach engendered by NEC that we were able to exceed the client’s expectations. Working on such a confined site with numerous party walls, the design and construction teams had to work extremely closely with each other to develop solutions that not only produced inspiring architecture but did this in a way that ensured buildability and safety.’ There were no reportable accidents on the project.

Paul Jolly, associate director of Dixon Jones, added, ‘From the lead consultant’s perspective, the project was delivered to a standard that exceeded our expectations for quality, which is unusual for design and build procurement. This was underpinned by the NEC collaborative ethos which extended to the relationships with key stakeholders such as teaching staff, parents, governors and council representatives.

‘For example, the team decided to accelerate the fit-out of a typical classroom ahead of programme to serve as a quality control benchmark to ensure all parties were happy  with the proposed finishes and quality prior to handover. The NEC contracts also supported a proactive approach to risk management in the form of early warning notices and compensation events.’

Recent Projects

Recent news

Richard Patterson – 100 not out for NEC

Richard Patterson – 100 not out for NEC

With this issue of the NEC Insights Briefing, Richard Patterson has now racked up an astonishing 100 contributions. We therefore thought it was time to learn more about the man behind it all.

Read more
NEC in the UK dredging sector: how to use Option selection and Contract Data to make it work

NEC in the UK dredging sector: how to use Option selection and Contract Data to make it work

NEC has become a mainstream form for UK dredging/coastal works, but it is not ‘one-Option-fits-all’. David Kinlan & Richard Patterson review how Option selection and Contract Data should be used.

Read more
Building better together: evolving construction contracts from adversarial to collaborative

Building better together: evolving construction contracts from adversarial to collaborative

Over the last three decades, collaboration has moved from being a desirable aspiration in construction projects to an explicit objective.

Read more
View all news