FAQs

The accepted programme should already be reasonably up to date. Assuming you have a requirement for 4-weekly submissions then it should be no more than 4 weeks old. If the contractor fails to submit programmes for acceptance when it should, or if the project manager has rejected its latest programme for a reason set out in the contract, then the project manager is required to make his or her own assessment of the compensation event (see clause 64.1, third and fourth bullets). In that case the project manager can use his or her own assessment of what the programme should be (clause 64.2).

It is different if the accepted programme is out of date because the project manager has not done what he or she should do, for example if the project manager has not replied to a programme submitted for acceptance (clause 31.3), or if the project manager has rejected a programme submitted for acceptance for a reason not stated in the contract. In either of those cases you use the out-of-date accepted programme, which is not satisfactory and certainly the project manager must strive to avoid this.

The project manager can instruct the contractor to provide a revised programme as soon as he or she is aware that the previous one is out of date (see clause 32.2, first bullet). On the other hand, the contractor may think that unfair if it does not take into account some time saving that has occurred in the meantime. The contractor can alleviate that by producing a new programme as soon as it is aware that the previous one is out of date (see clause 32.2, second bullet). It works both ways.

The 4 weeks is supposed to be a maximum not the norm. The contract encourages people to make sure they have an up-to-date and realistic programme, which is simply good management.



This website uses cookies, so that we can provide you with the best user experience.
By continuing to use this website, you are giving consent to cookies being used.
To find out more about which cookies we use and how you can manage them, please see our Cookie Policy