Best-project power tunnel

Best-project power tunnel

A strategic 330m long high-voltage electricity cable tunnel in central London is due to be commissioned early next year following successful design and construction using NEC contracts. The 2.44m internal diameter tunnel project  included a complex underground connection to an existing power tunnel containing 132 kV cables, which had to remain live throughout the works. The project won the Best Infrastructure Project at the 2018 Institution of Civil Engineers London Civil Engineering Awards.

The spur tunnel was part of a £42 million project by UK Power Networks to provide a major new 11kV substation to supply the Battersea and Nine Elms development area on the south bank of the River Thames. This includes the £9 billion Battersea Power Station redevelopment, home to Apple’s new London campus from 2021, plus the £1.2 billion Northern line underground railway extension and over 20,000 new homes.

The substation project was carried out under UK Power Networks’ £1 billion, seven-year Ed1son Alliance launched in 2015. Delivery member Clancy Docwra let the cable tunnel design to COWI under an NEC3 Professional Services Contract (PSC) and the tunnelling work to Joseph Gallagher Ltd under a £6.7 million NEC3 Engineering and Construction Contract (ECC) Option A (priced contract with activity schedule) in 2016. Gallagher subsequently engaged COWI under a separate PSC to provide permanent and temporary works design and monitoring.

Challenging project

The cable tunnel works involved sinking a 7.5m diameter, 30m deep shaft from within a converted warehouse at the substation site. The upper section was lined with pre-cast concrete segments while the lower section and launch tunnel used sprayed concrete. The open-face tunnelling shield then excavated the 330m long curved tunnel in clay using trapezoidal precast concrete segments fitted with waterproofing gaskets, passing under several live railway lines as it progressed.

At the end of the tunnel, a mass concrete 9m by 6m by 6m junction chamber was carefully created around the existing unbolted, wedgeblock lined, 2.95m diameter power tunnel using hand-mined timber-lined headings. The chamber was directly beneath a 1.6m diameter brick sewer and various other sewers and water mains.

Through reinforcing existing assets and careful sequencing and monitoring, the junction was safely and successfully completed in 2017 on programme and within budget – and without disruption to any existing services. The cable tunnel fit-out and substation works are scheduled for completion in the first quarter of 2020.

Track record

According to James Belcher, senior project manager at the Ed1son Alliance, ‘We chose to use NEC contracts for the challenging cable tunnel project because they have already been successfully used by UK Power Networks to deliver a large number of capital projects. NEC’s best-practice approach aligns with the company’s vision and values to be a respected corporate citizen, sustainably cost-effective and an employer of choice.’

He says NEC3 is a proven suite of contracts which is used throughout the utility, oil and gas sectors. ‘Our supply chain is familiar with the NEC3 suite and its ethos of improving ways of working, reducing duration through improved planning and methods of working, and reducing cost while improving safety. The contracts promote best practice and encourage people to work in a collaborative, open environment. They are also in plain English, logical and programme-based.’

Belcher says the NEC early warning process was used frequently on the cable tunnel project to mitigate risks and delays, particularly in relation to mining the junction chamber around the existing power tunnel and under existing assets.

‘For example, to allow the miners more space to work and reduce the number of concrete pours, COWI and Joseph Gallagher agreed at an NEC risk mitigation meeting to use sacrificial steel supports under the existing tunnel as an alternative to small headings. Comprehensive settlement monitoring within the existing tunnel, existing sewer and above ground provided the necessary assurance for this change of method.’

Recent Projects

Recent news

Case confirms NEC4 Y(UK)2 amendments in PSC, TSC and DBOC

Case confirms NEC4 Y(UK)2 amendments in PSC, TSC and DBOC

A recent court decision has affirmed that payment terms which make the final date for payment dependent on an invoice do not comply with the UK Construction Act.

Read more
NEC4 PSSC with a mix of prices and work on a time charge basis

NEC4 PSSC with a mix of prices and work on a time charge basis

Some people consider the NEC4 Professional Service Contract (PSC) too complicated for straightforward consultancy contracts.

Read more
How to resolve illegal or impossible requirements in NEC contracts

How to resolve illegal or impossible requirements in NEC contracts

NEC users should watch out for illegal or impossible requirements in the scope or contract terms.

Read more
View all news