London Stadium, UK

London Stadium, UK
  • location:
    Stratford, London, UK
  • Value:
    £323 million
  • Contracts Used:

    ECC Option A

  • Start-Finish:
    2013-2016
  • Employer:
    E20 Stadium LLP
  • Contractor:
    Balfour Beatty, Portview Fitout and Alto/Sapa
  • Project Manager:
    Mace

The £481 million 80,000-seat London 2012 stadium was the centrepiece of one of the world’s most successful and sustainable Olympic and Paralympic Games. Along with most other venues and infrastructure for the £7.3 billion games, it was procured by the Olympic Delivery Authority using NEC.

Four years later, the stadium has finally been transformed into a multi-use arena capable of delivering world-class sporting and cultural events – ranging from athletics, football and rugby to motor sport and concerts. It is now home to West Ham United football club and is the national stadium for UK athletics.

The £272 million transformation was again procured using NEC, though this time for E20 Stadium LLP. This is a joint venture of the London Legacy Development Corporation (LLDC) – which completed an award-winning £286 million transformation of the former Olympic Park also using NEC – and the London Borough of Newham.
 

MULTIPLE CONTRACTS

The stadium transformation work started in July 2013 when Balfour Beatty was engaged under a £41 million NEC3 Engineering and Construction Contract (ECC) Option A (priced contract with activity schedule) to carry out the main structural works. 

The existing roof was completely removed and a new 45 000 m2 roof – the longest cantilevered roof in the world – was installed, covering all seats and improving acoustics for matches and concerts.  It also re-uses the iconic floodlight towers, 6 km of cabling, 3800 lights, 1000 mechanical and electrical components and 19,000 t of demolition material.

Alto/Sapa was then engaged under ECC Option A to design and install an innovative retractable seating system, which extends the seating from 60 000 capacity in football mode to 80 000 in concert mode. Finally Portview Fitout completed the hospitality areas – including 16 executive boxes and 3600 corporate hospitality seats – again under ECC Option A.  

Project manager was Mace.

STOP-START SEQUENCE

Unusually the whole project had to stop half-way through so the part-finished stadium could host matches for the Rugby World Cup competition during September and October 2015. 

LLDC executive director Colin Naish says, ‘We had to pause the construction, bring the stadium back up to an operational standard exactly on time for the rugby, take it back into construction mode and then still complete everything on time for the summer 2016 events.’  These included a sell-out AC/DC concert in June 2016 and, more critically, West Ham’s first Europa league game in early August.

'NEC was perfectly able to deal with the unique stop–start nature of the works,’ says Naish. ‘Through the flexible structure of the contract, the careful drafting of the works information and the use of early warnings to flush things out as early as possible, we had clear visibility of the programme and our performance against it at all times. This was essential to ensure we met the various fixed events while staying within budget.’
    

BENEFITS OF USING NEC

  • NEC is now a tried and tested procurement method for delivering critically important venues and infrastructure exactly on time and within budget
  • NEC contract processes provide the client with full visibility of the programme and performance against the programme at all times
  • Through a flexible contract structure and careful drafting of works information, NEC enables successful delivery of complex construction/operation sequences
 

FURTHER INFORMATION:

Contact: Colin Naish, Executive Director of Stadium, Queen Elizabeth Park, London, UK
Tel: +44 20 3288 1872
Email: colinnaish@londonlegacy.co.uk
Web: www.london-stadium.com

Back to Previous PageBack

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

ECC Project Manager Accreditation

NEC training

Get the advanced skills necessary to be able to successfully manage a project using the NEC Engineering and Construction Contract (ECC), and become part of a unique group of accredited NEC professionals.

Read more

Submit your case study

NEC case study

Have you used an NEC3 contract in a project? Do you think your project would be an interesting case study for other NEC3 users? Then submit your case study.

Submit case study

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford