FAQs

They should be included, because the price for work done to date includes the costs of these subcontractors – see clauses 11.2(29) and 11.2(23). Of course the answer you come up with for the price adjustment is not added to the price for work done to date, instead it is added to the total of the prices (i.e. the ‘target’) – see clause X1.5.