Kennedy Town Swimming Pool Phase 2, Hong Kong

Kennedy Town Swimming Pool Phase 2, Hong Kong
  • location:
    Central and Western District, Hong Kong Island
  • Value:
    HK$671 million (£60 million)
  • Contracts Used:

    ECC option A

  • Start-Finish:
    2014 – 2016
  • Employer:
    MTR Corporation Limited
  • Contractor:
    Paul Y Construction Company, Limited
  • Project Manager:
    Stephen Hamill, MTR Corporation Limited

This multi-million project is for the covered section of the curvaceous part-indoor, part-outdoor complex. It replaces an original community swimming pool that was demolished to make way for the new Kennedy Town station on MTR’s HK$15.4 billion (£1.3 billion) West Island line railway, which opened in 2014.

MTR engaged architect Terry Farrell and consulting engineer WSP-Parsons Brinckerhoff to design the building, which has two outdoor pools, an indoor multi-purpose pool, jacuzzis and a filtration plant. The reinforced concrete structure features an elegant curved steel roof clad with pre-weathered zinc and PTFE roof.

Contractor Paul Y delivered phase 1 on time and within budget between 2009 and 2011 under MTR’s own form of contract, which is a conventional lump-sum type with non-contractually binding clauses to promote partnering.               

For phase 2, MTR sought to build on the success of phase 1 by adopting a more contractually binding form partnering – as offered by NEC. Being MTR’s first project to use NEC, it would also enable the corporation to evaluate how NEC compared with phase 1 – with a view to promoting further use of NEC in Hong Kong if it proved effective at delivery for all parties.

According to MTR project manager Stephen Hamill, ‘NEC has now been adopted as the contract of choice by government works departments, so it made sense for us to try it too. We are always looking to improve on our project performance, so trialling NEC back-to-back with the successful first phase is a true test of its potential benefits.’

INTEGRATED TEAM

From the outset of phase 2, an ‘integrated team’ approach was adopted by the employer, project manager, contractor, architect, consultant and government. ‘This was to ensure a thorough understanding of the common objectives for time, cost, quality, safety, environment and community expectations for project delivery,’ says Hamill. ‘MTR and Paul Y are fully committed to the NEC and to make it a success.’

Joint NEC workshops were attended by all parties both during tender and after contract award. A joint office, regular team training sessions, lesson-learnt workshops as well as partnering activities promoted close working relationship and effective communication, which in turn led to successful trust building. A ‘no blame’ culture was also fostered to encourage team members to express their views unreservedly to enable early identification and resolution of potential issues.

In addition, the site has received zero complaints from the public on construction activities to date. The project team regularly visits elderly homes in the vicinity and listens to the public’s views, which in turn help improve construction works performance and reduce public nuisance. The government’s Leisure and Cultural Services Department has been very supportive and complimentary on how the project has been advanced to date compared with similar projects.

SUCCESSFUL OUTCOME

Certainly the phase 2 contract is progressing well. Drainage diversions and reinforced concrete works were each completed four weeks early and the steelwork was two weeks early. In accordance with NEC requirements, both cost and programme status have been constantly updated throughout the contract. This has given the contractor the confidence to bring forward its projected completion date by four weeks and allowed MTR to activate bonus clause X6 for early completion.

‘In view of the fact that projected contract completion has been advanced by 4 weeks and compensation events have been kept within 1% of the contract sum, we have agreed in principle to give an early completion bonus to the contractor as an incentive to ensure early completion of the project,’ says Hamill.

Early settlement of compensation events has also enabled adequate cash flow for the contractor to honour its sub-contractors’ payments in a timely manner. ‘Our sub-contractors are all contented to be a part of the team,’ says Paul Y director and general manager Stanley Lo.

The project team is continuing its efforts to complete phase 2 successfully, thereby setting a firm precedent for MTR to consider adopting NEC for future railway development projects.

BENEFITS OF NEC3

  • Communication is enhanced among project team members through frequent discussions on potential time and cost implications required under NEC.
  • Potential project risks are identified through the NEC early warning system and effectively mitigated through the NEC risk reduction system, significantly improving productivity.
  • Details of risk-reduction measures are captured contemporaneously through the NEC compensation event system, helping expedite agreement on time and cost effects in a timely manner.
  • Project cash flow and cost control are improved through early agreement and payment on compensation events. Early agreement on compensation events also enables early conclusion of final account.
     

Further Information

Contact: Kam Woon Mak, Senior Design Management Engineer (Civil), MTR Corporation Limited
Tel: +852 35296008, +852 90978590
Email:  kwmak1@mtr.com.hk
Web: www.mtr.com.hk

Back to Previous PageBack

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

ECC Project Manager Accreditation Hong Kong

ECC Project Manager Accreditation Hong Kong

The Construction Industry Council and NEC are working in partnership to deliver this internationally recognised accreditation programme in Hong Kong.

Find out more

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford