Ministry of Defence using NEC4 to upgrade Clyde estuary submarine base in Scotland

Ministry of Defence using NEC4 to upgrade Clyde estuary submarine base in Scotland

The UK Ministry of Defence is using an NEC4- based framework to procure a £1.3 billion, 10-year refit of its nuclear submarine base on the Clyde estuary in Scotland.

Her Majesty’s Naval Base (HMNB) Clyde is the main home for the Royal Navy’s submarine service. The service operates nuclear-powered Vanguard class submarines, which carry the UK’s nuclear deterrent, and nuclear-powered attack submarines, which are currently based at both HMNB Clyde and HMNB Devonport in England.

Called the Clyde Commercial Framework, the refit involves a programme of replacement, refurbishment and new-build projects at the submarine base at Faslane and the nearby Royal Naval Armaments Depot at Coulport. This programme of works will enable HMNB Clyde to be a single integrated operating base for the whole of the UK’s submarine fleet by 2024, including the new larger Dreadnought class submarines that start replacing the Vanguard class in 2028.

The bulk of the programme consists of complex refurbishment of nuclear infrastructure in high-security operational areas. It also includes new accommodation and welfare facilities for the submariners relocating from HMNB Devonport and a state-of-the-art submarine training school.

NEC4 frameworks

In May 2018 the government’s Defence Infrastructure Organisation (DIO) awarded three 10-year NEC4 Framework Contracts (FC) for the Clyde refit to contractors VolkerStevin, Kier Graham Defence and Morgan Sindall.

Works packages from £1 million to £200 million will be allocated either by competitive tender or direct award. They will be let primarily under the NEC4 Engineering and Construction Contract (ECC) Option C (target contract with activity schedule) but with flexibility to use ECC Option A (priced contract with activity schedule), or ECC Option E (cost reimbursable contract) where appropriate. The NEC4 Engineering and Construction Short Contract (ECSC) will be used for small works and the NEC4 Engineering and Construction Subcontract (ECS) for subcontracts.

Services packages will be let under the NEC4 Professional Service Contract (PSC), Professional Service Short Contract (PSSC) or Professional Service Subcontract (PSS).

DIO appointed Mott MacDonald’s Glasgow office to provide the commercial expertise to develop the framework supported by DIO’s legal advisors Shepherd and Wedderburn LLP and independent collaborative behavioural specialists JCPii Ltd. DIO subsequently appointed Mott MacDonald as the NEC framework manager.

DIO commercial lead Ian Arbuckle says, ‘The contracts use the standard NEC4 terms and conditions with minimal use of Z clauses. Contractors are incentivised to collaborate and manage risk through framework-level key performance indicators, award fees and early completion bonuses.’

He says the framework also encourages and provides a contract mechanism for early contractor involvement. ‘This enables contractor input into the scope, programme and cost estimates for each package, helping to ensure it is delivered safely, on time, within budget and with minimum disruption to the base.’


Changing behaviours

 

Arbuckle says a key objective of the framework was to encourage a more collaborative approach to working in such a high-security, highly regulated and highly congested operational environment.

‘Historically HMNB Clyde has not been an easy place to work. The framework provides for joint collaborative behavioural training for all parties to help them work in NEC’s required “spirit of utual trust and co-operation”, as well as joint NEC training.’

He says the framework requires face-to-face structured dialogue workshops for each package to discuss and understand its scope, constraints and each party’s issues. ‘We will also hold launch workshops to discuss the contractor’s tender and how all parties can make it more effective.’

A senior leadership team consisting of the DIO framework director, each contractor’s framework director and the framework manager meets monthly to steer the framework, set up the collaborative business processes, resolve disputes and score key performance indicators (KPI).

‘KPIs for each framework contractor are scored every month based on their performance in each package they are implementing and their overall collaborative behaviour. KPI scores are moderated by the client’s performance in each package and overall collaborative behaviour, such that they can increase. The contractor’s performance is then linked to payment of a monthly award fee on each of their packages, comprising an element of their fee matched by the client,’ say Arbuckle.

 

BENEFITS OF USING NEC

  • NEC provides a comprehensive suite of back-to-back contracts for frameworks and individual works and services packages, with lump-sum, target cost and cost-reimbursable procurement options.
  • NEC obligation of parties to work in a ‘spirit of mutual trust and co-operation’ promotes collaborative behaviours, helping to ensure works are delivered safely, to time and budget and with minimal disruption to operations.
  • NEC flexibility enables framework contractors to be incentivised to collaborate and manage risk through framework-level key performance indicators, award fees and early completion bonuses.
  • NEC provides a mechanism for early contractor engagement, enabling contractor input into the scope, programme and cost estimates for each works and services package to maximise efficiency and value for money.
 

 

Recent Projects

Recent news

Trained to Deliver: new NEC Contracts research maps the gap between belief in training and investment in it

Trained to Deliver: new NEC Contracts research maps the gap between belief in training and investment in it

NEC Contracts has published Trained to Deliver..., the third in a series of global research studies following 2025's Transforming Construction and 2026's Trust, Contracts and Outcomes.

Read more
2026 NEC Training in the UK

2026 NEC Training in the UK

From new starters to experienced professionals, our 2026 training equips you to navigate NEC contracts with clarity, manage risks effectively, and deliver projects collaboratively.

Read more
NEC Contracts and Project 13 publish new guidance on NEC for Enterprise models

NEC Contracts and Project 13 publish new guidance on NEC for Enterprise models

NEC Contracts and Project 13 have jointly published new guidance on the use of the NEC4 suite within Enterprise models.

Read more
View all news