East London Line, London, UK

East London Line, London, UK
  • location:
    London, UK
  • Value:
    £650 million
  • Contracts Used:

    ECC, ECS

  • Start-Finish:
    October 2006 - April 2010
  • Employer:
    Transport for London
  • Contractor:
    Balfour Beatty / Carillion joint venture
  • Project Manager:
    Parsons Brinckerhoff

Joint-venture design and build contractors Balfour Beatty and Carillion completed the new 21km London Overground railway between Dalston Junction and West Croydon in April 2010, a full two months early. Working under an NEC3 Engineering and Construction Contract (ECC) option C (target cost contract with activity schedule), they provided Transport for London with complete operating railway system in just three and a half years.

The project involved refurbishment and extension of the former East London line with extensive new track, structures, power systems and signalling and new step-free stations at Dalston, Haggerston, Hoxton and Shoreditch. A total of 3.5km of the route runs on new and refurbished viaduct and a further 3.2km is in existing tunnels, including the historic 1843 Thames Tunnel river crossing.


Managing interfaces



According to London Overground Infrastructure Director Peter Richards, "From the start we stressed to everyone that this job was about delivering an operational railway infrastructure, rolling stock and operations.

That is why we went for a single NEC3 design and build main works contract. It has meant that Balfour Beatty Carillion has managed all the systems interfaces, and all the responsibility has rested with one party of get on and do the whole thing."



Requirement driven


Joint venture Project Director Mike Casebourne says, "When we signed the contract in October 2006 we had to remember that we had committed to design, construct, test, commission and deliver an operational railway, not just its separate structures and rail systems.

It was a requirement driven contract for example to design for three minute headways between trains", he said. Services on the northern section between Dalston and New Cross opened on 27 April 2010, with the southern section following on 23 March 2010 to coincide with the national timetable change.

Parsons Brinckerhoff acted as programme manager with Davis Langdon as cost consultant and Mott MacDonald as the client's technical adviser. Scott Wilson and Tony Gee and Partners provided design services to the contractor.


Orbital railway


The project is the first significant move towards creating an orbital railway for London, connecting 20 boroughs and bringing huge regeneration opportunities to some of the capitals most deprived areas.

Phase 1, being completed in 2011, creates a link with the recently opened London Overground service between Clapham Junction and Stratford at Highbury and Islington. Phase 2, due for completion in 2012, runs between Clapham Junction and Surrey Quays, completing the orbital railway.


Integrated subcontracts


The ECC and NEC3 Engineering and Construction Subcontract proved capable of application to each of the civil engineering, building and rail systems sections of the works. These were provided through a matrix of 450 subcontracts, plus a similar number of material suppliers, each from £10,000 to £25 million, 95% of which were settled within 6 months of completion.

A systems integration approach was adopted from the start, using progressive assurance to check that at every stage of the design and construction process each structure, building and rail system was exchanging the desired inputs and outputs with its internal neighbours and external stakeholders.

These were primarily the demand for and distribution of high voltage, low voltage and direct current power between systems provided by separate subcontractors, and the exchange of electronic data between systems provided by separate subcontractors. The subcontractual framework had to accommodate a multitude of adjustments and changes as they progressed 

Further Information

Contact: Peter Richards, Director, London Overground Infrastructure
Tel: +44 020 7826 4870
Email: peterrichards@tfl.gov.uk
Web: http://www.tfl.gov.uk/

Back to Previous PageBack

NEC CONTRACT FINDER

Not sure which
contract you need?
Start Finder

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q2. What is the risk / complexity level of your project?

Q3.What type of contract do you require?

Q3.What type of contract do you require?

Engineering & Construction Short Contract The Engineering & Construction Short Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Short Subcontract The Engineering & Construction Short Subcontract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Contract The Engineering & Construction Contract is the most appropriate contract for your project:
View Contract X

Engineering & Construction Subcontract The Engineering & Construction Subcontract is the most appropriate contract for your project:
View Contract X

Professional Services Short Contract The Professional Services Short Contract is the most appropriate contract for your project:
View Contract X

Professional Services Contract The Professional Services Contract is the most appropriate contract for your project:
View Contract X

Term Service Short Contract The Term Service Short Contract is the most appropriate contract for your project:
View Contract X

Term Service Contract The Term Service Contract is the most appropriate contract for your project:
View Contract X

Supply Short Contract The Supply Short Contract is the most appropriate contract for your project:
View Contract X

Supply Contract The Supply Contract is the most appropriate contract for your project:
View Contract X

Framework Contract The Framework Contract is the most appropriate contract for your project:
View Contract X

Adjudicators Contract The Adjudicators Contract is the most appropriate contract for your project:
View Contract X

Contact NEC Contact the NEC Team for further advice
View Contract X

X

Related Products

NEC Users' Groups

NEC Users

Discover a range of exclusive benefits, discounts and networking opportunities with the NEC Users' Group

Find out more here

Copyright © NEC® Contracts 2014, all rights reserved.
NEC® is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers.
Company Reg. No. (Thomas Telford Ltd): 2556636. VAT Reg. No: 240877747.

Institution of Civil Engineers Thomas Telford