Virgin Media chooses NEC4 for over £2.5bn cabling works

Virgin Media chooses NEC4 for over £2.5bn cabling works

Virgin Media, which provides cable-based telephone, television and internet services to 6 million customers in the UK, has chosen NEC4 contracts to deliver over £2.5 billion of cable installation and maintenance works during the next 7 years.

An initial tranche of 18 NEC4 Engineering and Construction Contract (ECC) Option A (priced contract with activity schedule) and Option B (priced contract with bill of quantities) contracts were let last summer for cable network infill projects, ranging in value from £150,000 to £12 million. The NEC-procured infill build programme will continue at a rate of around £200 million a year.

In addition, nine NEC4 Term Service Contract (TSC) Options A (priced contract with price list), C (target contract with price list) and E (cost reimbursement) were let in March this year for smaller regional cable installation and maintenance works worth a total of around £250 million a year. The five-year contracts started In April and can be extended by two years.

Expanding network

The NEC-procured works programme primarily involves extending, upgrading and maintaining the company’s 186,000 km local cable distribution network, which currently passes 16 million UK and Ireland homes and businesses. Its gigabitcapable fibre-optic-cables run between 330 ethernet nodes and 38,000 cabinets in shallow trenches, typically 80mm wide by 550mm deep in roads and 350mm deep in footpaths.

In addition to expanding the network to reach more homes, other works being delivered through the programme include installing new and upgraded cabinets, replacing batteries, fixing faulty connections, undertaking emergency restorations and diverting services.

Most of the contracts are considered low risk, hence the predominant use of NEC lump-sum options A and B for the TSC and ECC contracts respectively.

Driving integration

Commercial director Chris Matthews says, ‘We chose NEC contracts to replace the heavily amended ICE contracts we used to use. NEC will help us to drive greater integration, trust and sharing of risk, which in turn will deliver better value for our customers, shareholders and supply chain.’

He says some contractors already had NEC experience through working with water, gas and other utility companies. ‘We nevertheless organised an extensive NEC training programme for staff and suppliers together with our commercial consultant Arcadis, legal adviser Ashurst and contract management system provider Cemar’.

Matthews, formerly director at EY and programme director for Highways England’s NEC-based Routes to Market programme, says it was still a steep learning curve for some contractors. ‘The key was getting them to adopt the NEC culture of integration and collaboration, understanding that it is not about us beating up the supply chain or them trying claim whatever they can.’

Improving productivity

He says the ECC infill contracts are working very well, promoting much better collaboration and integration between the commercial team and the supply chain.

‘The introduction of early contractor involvement has significantly helped with planning and pricing of individual contracts. Cost-overruns have been cut from previous levels of around 10% to 2.5%, resulting in much lower contingencies, and contractors are making better margins.’

He adds that better planning and NEC’s transparency, incentive mechanisms, early warnings, compensation events and fairpayment processes have significantly improved productivity, helping to achieve an overall 30% reduction in infill build costs.

‘The integration of planning, expansion and maintenance over larger geographic areas in the regional TSC contracts also means these are expected to deliver more continuous workflows for contractors, enabling greater optimisation of resources and significant improvements in productivity.’

Recent Projects

Recent news

NEC4 Clause 10.2 - a practical and philosophical approach

NEC4 Clause 10.2 - a practical and philosophical approach

This article provides both a practical and philosophical analysis of Clause 10.2 and the importance of leadership in putting its principles into practice.

Read more
Value engineering under Clause 16 of the NEC4 ECC

Value engineering under Clause 16 of the NEC4 ECC

NEC4 ECC Clause 16 ‘Contractor’s proposals’ is a value engineering clause. It encourages contractors to propose changes to the clients’ scope which will reduce the amount clients pay.

Read more
What NEC4 ECC supervisors do, and need to know

What NEC4 ECC supervisors do, and need to know

The NEC4 ECC supervisor is an invaluable member of the site team, focusing on quality and helping the contractor to get things right.

Read more
View all news